Imagine having a place to walk, run, or ride your bike that connects your neighborhood with parks and everyday destinations. That is the promise of the Ludlam Trail, a project Miami-Dade residents have spent years waiting to see take shape.
As of October 2026, there is meaningful progress to report. There is also a longer road ahead than a design-contract announcement might suggest.
The clearest answer? The trail is advancing, with initial construction anticipated in 2028. However, a substantial funding gap remains, and the county’s published schedule does not establish an opening date for the entire corridor.
What Would the Ludlam Trail Bring to Miami-Dade?
The planned 5.6-mile greenway follows a former railroad corridor between NW 7th Street and SW 80th Street, generally between 69th and 70th Avenues. Its route crosses both the City of Miami and unincorporated Miami-Dade County.
Plans call for an 18-foot-wide shared-use path, along with landscaping, shade trees, lighting, seating, and connections to surrounding neighborhoods.
For residents, the appeal is easy to understand: more opportunities to get outdoors and potentially make some local trips on foot or by bicycle. The county also envisions links with its broader trail network and toward Dadeland North Metrorail Station.
Those connections remain part of the project’s vision. They should not be confused with a fully accessible route available today.
What Has Actually Moved Forward?
Miami-Dade acquired the corridor in 2018, and its Project Development and Environment study was completed in 2023.
A significant milestone followed on July 21, 2026, when county commissioners approved a professional services agreement with Kimley-Horn worth up to approximately $9.53 million.
That agreement supports design and related professional work. Its five-year term should not be read as a promised opening date.
The county’s October 5 project presentation offered a more detailed picture of what comes next. Phase 1 focuses on an area adjacent to A.D. Barnes Park, positioning an existing community destination as an anchor for the trail’s early development.
This gives residents something more concrete to follow: a phased delivery strategy, rather than simply a vision for the entire corridor.
When Could Construction Begin?
The October 5 presentation outlined these anticipated milestones:
- 2027: Complete Phase 1 construction documents and begin its permitting and federal procurement process.
- 2028: Begin and complete the at-grade portion of Phase 1 construction, start the first bridge, and complete design of the entire trail.
- 2030: Complete construction of the first bridge.
These are planning projections, subject to change. Importantly, first-bridge completion is not the same as completion of the full greenway.
The county says completed portions will open for public use. Residents may therefore gain access to sections before the entire route is connected.
Why Is There Still a Wait?
Funding remains a major hurdle. In its October presentation, the county identified approximately $154.6 million in design and construction costs, $47.8 million in secured funding, and a $106.8 million construction shortfall.
The physical work is also substantial. Plans include four roadway overpasses, two canal bridges, and 11 at-grade road crossings. The roadway bridges are planned at Flagler Street, SW 8th Street, Coral Way, and Bird Road.
The former rail corridor also requires environmental remediation. The county’s design agreement includes coordination and review related to that work.
Together, those requirements help explain why delivery involves engineering, approvals, and funding decisions well beyond laying pavement.
What Should Nearby Buyers and Homeowners Watch?
For anyone considering a home near the corridor, future trail access is a useful lifestyle consideration. The practical questions are specific: Where will the nearest entrance be? How would you reach it? Which section is scheduled to open first?
A.D. Barnes Park is planned as a primary trailhead, making access around that location particularly worth understanding.
Buyers should evaluate a home’s current surroundings alongside future plans. Sellers can discuss documented improvements while keeping proposed amenities and completed features clearly distinguished. Neither proximity nor an announced timeline guarantees appreciation.
Final Takeaway
The Ludlam Trail has a design team, a phased strategy, and published milestones. Those are meaningful advances. The next tests will be completing design, closing the funding gap, and turning planned construction into usable sections.
Find a Miami Neighborhood That Fits Your Everyday Life
Considering buying or selling near the Ludlam Trail? Call, DM, or email Jeannie Montes de Oca to discuss neighborhood amenities, current property options, and how future improvements fit your plans.
Jeannie Montes de Oca
Miami Realtor | Luxury Real Estate Professional
Ranked top 3% nationwide Berkshire Hathaway Home Services & Chairman Diamond Level # 5 Individual Producer for Coral Gables Office